R Fahey Racing Stables, Malton

Project:     Racing Stables, Malton 
Package:  Redi Rock
Client:       R Fahey                    
 
The project at RF Racing Ltd was undertaken in the summer of 2010. Redi Rock was chosen after the contractor compared both costings and the superior finish of Redi-Rock as opposed to gabions.
 
The contractor was impressed by the advantages of Redi-Rock. Not only did it provide a retaining wall with a look of natural stone to blend into the existing landscape, but it also provided crucial savings in both time and money.
 
The overall project took 6 days to complete and the saving was 43% compared with the same project using gabions.
 
Project value: £24,000